FWD-IP completed an extensive audit of all existing services including Fibre Optic, voice and other services so when the pile driving was to start this did not affect the College with their communications in any way.
All cables had to be documented with detailed site plans being submitted with existing cable routes as well as the new proposed routes.
Once the contract was appointed to FWD-IP the contract the team could then start work. This involved phasing the project to fit in with the College teaching time table as well as being aware of completing the workings with the dead line so the Pile Driving works could commence.